Hi All
I have created a simple Project with Internal Network Activity (NWA).
Plan Version 0 has been updated with appropriate planned cost.
Partial Confirmation has been posted.
Forecast work is greater than actual work in the Dates TAB of the Internal NWA
Scheduled finish dates are in current period or greater.
When we execute CJ9L no objects are selected for processing? Can anybody please expalin why this may be the case.
I do not believe there is any outsatanding configuration? The costing variants must be working to enable calculation of the Plan Version 0 amount.
System calculates forecast values only for activity account assigned networks. Check whether your network is activity account assigned or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.