Is it possible to create production order without planned order(from MRP) and without Routing. Can anybody give the sequence of transactions.
very urgent and helpful answers immediately rewarded.
vps
Hi vps
You cannot create prod order directly through MRP run.
MRP run will create either PR OR Plan order first then only prod order / purchase order can be created by conversion.
If you want to create prod order without plan order. Create it manually through CO 01
Creation of prod order without Routing is possible. But you should have default operation.
At the time of creating prod order. The system will display no task list selected. Either cancel or select operation. You should select default operation.
Hope this is clear
Regards
J . Saravan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.