Process Order Numbering

Former Member
0 Kudos

Hi Gurus,

In my case, Number range object for Process Orders has been defined in CO82.

Suddenly some process orders have different naming 14XXXXXX instead of 72XXXXXX.

I would like to know what else affects the determination of Process order numbering.

View Entire Topic
Former Member
0 Kudos

Hi,

Just check the Process order type, whether its same to both process order numbers. If not then check the assignment of process order type in Plant (OPPQ)/ MRP group parameter (OPPR).