on 06-02-2011 2:15 PM
Hi
I have a scenario in which engineer to make products are being manufactured, that can be mapped with PP.
Since we require PS for earned value analysis we need to calculate POC (Progress) from PP order. Now:
1- Can we calculate plan and actual POC (progress) of production order like PS ?
2- Is their anyway we can integrate PP/PS for calculating plan and actual POC and update POC in PS Project ??
Your inputs will be highly appreciated.
Regards,
Kashif
Yes Possible, you need to maintain measurement method for Order types.
Please refer..
SPRO >> PS >> Progress >> Progress Analysis >> Enter Measurement Methods for Order Type
Also read the help file for this node.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.