I am facing an issue ,where shift "NIGH" is not defaulting (shift is empty) in the production order confirmation (CO11N), done during the start and end time defined at the shift definition for "NIGH" shift.
This works fine for other shifts.
Shift definition for the shift groups are defined as below.
Gen1 and Gen2 shifts to be selected randomly , for the same work center whenever required, other wise the shift
should be proposed based on the time
*shift proposal is set as "1.Current date" in confirmation parameters for the plant and order type.
*Default value for shift is set as "2-order type dependent shift" in OPK0
*No shift sequences maintained
Please let me know the reason behind this, where only "NIGH" shift doesn't get proposed?
Is it because the start and end time span across 2 dates (from 10 P.M to 5.59 AM next day)?
Resolved with the below steps.
1.Define shift definition, the start date should be > =01.01.1980 as suggested by an incident raised with SAP support.
2.Define shift sequence
3.Assign the sequence to the interval in the work center capacities tab
can update the sequence by adding extra shift to the work center.Included without start and end times so that the shift can be selected at confirmation if required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.