on 01-21-2008 12:57 PM
Sir,
User has made UD on today(21.01.2008) but that material was recieved on 19.12.2007
date of lot origin is 19.12.2007
but when I wants to consume it on 31.12.2007.
when I am doing MB1A with 201 movement,
sysem is giving me error " Deficit of SL Unrestr. prev. 10 KG : RLACET-CH 1023 RM00"
now what i have to do
is it any possiblity for this
any reverse option please suggest me.
Thanx
Regards,
Nilesh Ithape
Hi,
you can go to qa 11 then in their you change the date itself as 31.12.2007 then it will allow to do that and also the period should remain opened for that period
reward points if useful to you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.