Planning calender not working

former_member254501
Active Participant
0 Kudos

We have factory calender set up working 7 days and planning calender for 5 days but still planned order/PR are generated on saturday. using standard lot size pk

period looks ok

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Have you assigned the planning calendar to material master?

You may try an option of 'Do not displace' regenerate period and run MRP again.

Also Do you have GR processing time in the Material Master?

Best Regards,

R.Brahmankar

former_member254501
Active Participant
0 Kudos

I have assigned it in material master as well tried all types for option but still not sure ...also GR time is 0

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please share the screen shot of lot size PK from OMI4 setting and also share screen shot of planned order details.

Best Regards,

R.Brahmankar

former_member254501
Active Participant
0 Kudos

maintained shcduling in omi4 and it worked