PIR date at start of month

kalidindi_varma
Explorer
0 Kudos

Hi Planning Experts 

When creating PIR in demand management requirements are assign to 1st day of the Month. But business want to assign last day of the month. 

Based on few post in the community i tried OMI4, it is not working as the customer requirement fulfillment is also assign to last day of the month. 

https://community.sap.com/t5/enterprise-resource-planning-q-a/pir-date-at-start-of-month-week/qaq-p/...

Regards, 

Varma 

Accepted Solutions (0)

Answers (1)

Answers (1)

DominikTylczyn
Active Contributor
0 Kudos

Hello @kalidindi_varma 

Typically PIRs are created in monthly buckets, i.e. on the first day of a month. I don't think you can change the day assignment for monthly PIR. However you can create PIRs with planning period = 😧

DominikTylczyn_0-1713853613763.png

This way you can specify an exact date of a PIRs as the last day of a month.

Best regards

Dominik Tylczynski