Pending planning order no.

Former Member
0 Kudos

Sir i got 100 sales order of different materials , out of which i had run MRP of 70 sales orders ie i had converted those 70 sales order into planned order , now i want a list of those 30 materials whose MRP is not yet run. How to get that list ?

I am online.

View Entire Topic
vikas_koul2
Explorer
0 Kudos

Hi Abhijeet,

u have converted the 70 SO into planned orders and 30 are yet to be converted so u can see the list of 30 orders in MDO4 only as customer order.this is because these have not been yet converted.

before running the MRP(MD02),the MRP List (MD05) will be created based on the inputs in the control parameters.The MRP list always displays the future stock/requirements situation at the time of the last planning run