on 07-20-2009 11:29 AM
Hi
I have done setting for PR over all release.
I have selected indicator Overall release PR while configuring release group.
Then I have selected over all release indicator in Define document type.
But the release is not triggering for overall release
Is there any other setting for PR overall release.
Please help
Regards
Sunil
Please go to
SPRO -> MM -> Purchasing -> PR -> Release Procedure -> Procedure with classification -> Setup procedure with class -> Release strategies.
Click on individual Release Strategy, click on simulate release.
Also check all assignment using T code CL20N like Plant, Pur Org, Value etc.
Will give error, if any.
Regards
Bhavesh Mistry
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.