on 11-19-2008 3:12 AM
Dear all,
I am trying to do a re-org for an employee and i got this error "Organization assignment created via organization management" Message no PB 300.
Anyone have idea how to solve it?
Thanks
Regards,
Bryan
Hi.
Its just a warning message. Pls go ahead with creating the record. Its because of maintaining 1008 IT for the Position u have choosen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Thanks for your fast respond. I have done some investigation and i found that in po13 (put in the employee position)...there are 2 cost center assignment
1) 01.01.2008 - 01.07.2008- Cost center ERC 5003
2)02.07.2008 - 31.12.9999 - Cost center ERC 5008
If i change the "02.07.2008 - 31.12.9999 - Cost center ERC 5008" to cost center 5003. The error message will disappears. Anyone know why this the cost center ERC 5008 will give me that error message?
Thanks
Regards,
Bryan