Hi Experts,

I have assigned Object Information key to Order types and Notification type with out assigning to technical object. Still I got Object Information popup details when the threshold vale reached.

Could you please explain me why we assign "Object Information Key" to  Equipment and Functional Locations.

What is the benefit on that assignment.

Thank you.

View Entire Topic
jogeswararao_kavala
Active Contributor
0 Kudos

This gives you the statistics of Maintenance activities such as Breakdown Notifications Orders etc, when you attempt to create a Notification/Order on a particular technical object (Equipment/FLocn). i.e., Suppose you are creating a Notification > As soon as you enter the Equipment and press Enter a pop-up appears infront of you giving the above statistics. Also drill-downs are possible from these figures in the pop-up.  If this information window  is not useful to you then you can de-assign this from spro settings, which you already knew.

See these useful links:

Define Object Information Keys (Though it is explained for CS, it is applicable to PM too)

Object Information Window pop up

Regards

KJogeswaraRao

former_member217512
Participant
0 Kudos

Hi Jogeswara Rao, Maria,

Thank you for the comment. I think you are clear with my doubt.

In SPRO we have option to assign the Object information key to

1)Functional location Category

2)Equipment Category

3)Maintenance Order Types

4)Maintenance Notification Types

Case 1.

I have assigned Object Information key to both Order types and Notification types only.

Then when I create some orders/Notifications for equipment/Functional Location, I got the automatic popup as the threshold value reached.

Case 2.

I have assigned Object Information key to both Equipment category and Functional Location Category only.


Then when I create some orders/Notifications for the equipment/Functional Location,I didn't get any automatic popup even after the threshold value reached.



My doubt are:

what is the significance of  assigning Object Information Key to Equipment category and Functional Location Category?

Did I missed any settings?




jogeswararao_kavala
Active Contributor
0 Kudos

Hello Renjith,

For example the assignment of OIK in Equipment Category adds this icon in Equipment master (IE02/IE03) giving rise to the shown pop-up (obviously, when clicked).

Regards

KJogeswaraRao

former_member217512
Participant
0 Kudos

Hi,

I Understood the difference. Is that is the only benefit of assigning OIK to Technical object Category?

jogeswararao_kavala
Active Contributor
0 Kudos

Hello Renjit,

It is Yes. Because usually the same OIK we assign to all these objects. Also the other benefit of OIK as I touched upon earlier is the short-cuts to go to the respective detailed reports by using the push buttons provided such as:

You have more in horizontal (for Scheduling etc)

Regards

KJogeswaraRao

former_member217512
Participant
0 Kudos

Hi Jogeswara Rao.

I got the concept. Thank you very much for support.