MRP Run

Former Member
0 Kudos

Dear Expert

We have a pharma organization so we follow proces industry, In our organisation we have central warehouse ,different sales depot and manufacturing plants , presently MRP run is done at Manufacturing plants only, rest we have maunal procedure . Now we want MRP run should be done at Depot and warehouse also which are also plants , requirement is such that when each Depot Run the MRP for their respective requirement and the result of MRP run will be stock tranfer oder .in this way all other depots will do the job , the consolidated requirement from all the depots will come to warehouse and warehouse will also run the MRP and the here also result will be stock transfer order . At last MRP is run at manufacturing plant here all the Purchase requisition and other planned order will be generated. How can we map the same in System

Regards

View Entire Topic
Dsk
Active Contributor
0 Kudos

1.Define Scope of Planning for Total Planning(opoe)

1.1 - Define a scope of planning like ( ZMRP)

1.2 - Define the sequence ofplants for MRP run with counter / plant ETC

For example your sequnece should be

1-Depot ( all the depot plant number

2-warehouse ( all the warehouse plant number)

3.manufacturing plant ( all your mfr plant number

2.Once you have then in the Md01 and run the MRP

here it will run in the sequence defined in teh counter

reg

dsk