MD11 generates qty for discontinued component

christineee
Explorer
0 Kudos

Hello Everyone,

MD11 - user do manual creation of pld ord. in MD11, MD11 still assigned qty in the discontinued component instead of follow-up material. (as checked, this can be corrected after MPS run)

Question:

Since the user is using Manual Creation, is there a way around to change planned orders to consider the follow-up material or transfer the qty to the follow-up material.

Or this should be already customized program by ABAP?

This is in SAP ECC. Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

RAHEEL_BABAR
Active Contributor
0 Kudos

Hi,

If the user is manually creating planned orders in MD11 and the system is assigning quantities to the discontinued component instead of the follow-up material, this behavior may not be able to be changed without customizing the program through ABAP.

Regards

christineee
Explorer
0 Kudos

thank you!

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

MRP will redirect the quantity to the follow-up material once you plan the discontinued product.
Regards,
Caetano