on 10-01-2009 12:11 PM
Hi, for some materials, we need to keep some extra material to process in operations. say, a sheet of 2.2x4.2 metrs square is required to make one product. after making that product, it actually consume 2x4 m2 only. we need to keep that much extra to porform the opration. how to show this extra mat of 0.2x0.2 m2 (scrap is planned) for this material? is there any way can we show the reason for extra consuption of material in pp? pls advise.
Hi,
1. If you want system to plant component quantity including scrap qty then mention scrap percentage in line item of BOM component.
2. If you want to issue extra components then issue with MB1A with movement 261 mention order number.
you can see that consumtion with order table AUFM.
Regards,
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.