on 02-13-2012 9:39 AM
Dear expert
I have a four operation in routing with following condition Please help to map these
First operation need to strart on monday and finish by tuesday evening-Material assigned is XXX
Second operation will start on monday after noon and finish by monday evening-Material assigned is yyy
Third operation will start on tuesday morning and finish by Tuesday evening-Material assigned is zzz
And final operation is start by wensday moring and finish by wensday itself
As the second and thrid operation days is same as first operation how system will schedule all in same days
Thanks in advance
AF
Hi
Define 2nd and 3rd operation as parallel to 1st operation. You can select Scheduling if you want since these 2 operation will run in sequence. I leave that to you. Depends if you wish to do capacity planning for them or not.
Assign 1st and 4th operation as main operation and keep all the requirment in control key.
Component assignment is your pick.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You Can maintain Queue time in parallel operation or buffer time in parallel operation. This will ensure that the operation starts after 5 HRS only. Use operation 1as referece for the parallel operation. Once youcreate the operation 2 and 3 in parallel then maintain Std Queue time and Min. Queue time as 5 HRS. This will ensure that these operation are schelduled after 5 HRS only.
Try the link below for more details. I hope this will help.
http://help.sap.com/erp2005_ehp_06/helpdata/EN/45/a91b49ab7311d189090000e8323492/frameset.htm
Edited by: ANIMESH KUMAR on Feb 13, 2012 4:56 PM
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.