Hello all,
In a plant they produce a customer specific semi-finished which is packaged in different formats.
When a sales order is created for one of the MTO finished goods that will trigger the production of the semi-finished. The lot-size of which is larger than requirements from single order line. Therefore customer must make sure that total requirements from sales order lines matches quantity of semi-finished. The problem is that with normal MTO SAP will create one planned order for the semi-finished for every sales order line. Instead I want single planned order to cover customer requirements.
This shoud be make-to-order production of semi-finished good and the finished goods and want to have forecast on the finished goods.
Somebody solved this before?
Best regards,
Tor Holter
Oslo, Norway
Hi Tor,
As I understand: you want your SFG to have separate PldOrd for each SO of FG.
What about individual/collective requirement setting? Cannot you solve your problem via this?
http://help.sap.com/saphelp_47x200/helpdata/en/ea/e9b4ae4c7211d189520000e829fbbd/frameset.htm
Regards,
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
13 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.