on 01-28-2009 7:51 AM
Hello Exoperts,
I am trying to copy a plan using Tocde KP 97.
While Executing error is showing that
Transaction Planning primary costs has been locked
Pls help
Thanks
Guru
Hi, Thru transaction OKP1, unlock the business transaction primary costs planning for the selected period. Trust this helps much! Cheers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
9 | |
7 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.