on 09-01-2014 8:20 AM
Hi,
I am trying to make delivery from the project.
I deleted one line item of material from activity and add another material.
when i am trying to create delevery from the N/W activity for new material , system is picking the deleted material for delivery.
Can anybody suggest.
Thanks & Regards,
Sudhindra
Hi Anand/Varun,
Thanks for your inputs and interest.
Actually I want to know how delivery of material happens in Investment project,I mean business process.
Let me explain the whole scenario.
1) User created material (BOM) below an internal activity(below Network). PR created ( Collective PR activated).
User later deleted the material later. In cn23 tcode in material line item view the status is "DEL REL"
2) User later created new material under same internal activity.PR created (collective PR).
User did PO,GR & Invoice reciept done for the material,
We are using custom transactions for the delivery of the material from project. Delivery is not happening error message is " item flagged for deletion in the network ".
The WBS status above the internal activity is TECO.
Please suggest for this issue. The main thing is I want to know what is the business process for delivery of material from the project.
Thanks in advance.
Sudhindra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Sudhindra,
For Delivery through project , Material is assigned and wbs,activity should be in release stage.
Please check that also.
Also check reservation that you have created while assigning material.
Normally, for delivery through project process.-reservation through wbs-element work.
Please check these all.
Thanks & Regards
Rahul Bansal
Hello Sudhindra,
Status of the material which you are trying to deliver should be in Released status.
Try revoking status of WBS element from TECO and then retry doing delivery.
Following are the constraints for Delivery from the Project.
Regards
Tushar
Hi Sanjeev,
Thanks very much for your basic inputs on delivery through project.Sorry for delay in response. Issue was it was Z transaction for delivery of material. After debugging Error got was " No checking group maintained for the material & Product".
If you can provide ideas & input that would help a lot.
Thanks & Regards,
Sudhindra
Hi Tushar,
Thanks very much for your basic inputs on delivery through project.Sorry for delay in response. Issue was it was Z transaction for delivery of material. After debugging Error got was " No checking group maintained for the material & Product".
If you can provide ideas & input that would help a lot.
Thanks & Regards,
Sudhindra
Hi rahul,
Thanks very much for your basic inputs on delivery through project.Sorry for delay in response. Issue was it was Z transaction for delivery of material. After debugging Error got was " No checking group maintained for the material & Product".
If you can provide ideas & input that would help a lot.
Thanks & Regards,
Sudhindra