on 04-21-2008 2:14 PM
Dear All,
We are having the scenario that we need to allocate budget for internal orders. Meanwhile we need to allocate the budget amount for cost element as planning based on the internal order. But both amount are not same.
For e.g.,
Internal order Budget (KO22) may have USD 40,000.
Cost element planning (KO12) based on the internal order may have USD 20,000
During the document entry, the user wants to get the Error or Warning message when the budget exceeds based on the relationship between Internal Order and Cost Element.
How do I bring the scenario?
I request you to all, please reply.
Regards,
Ranesh.
Hi
Set the tolerance limit, level at 3 (Availability control) for internal order.
Rgds
Aman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.