on 09-27-2012 2:28 AM
If I want to be able to carry out all functions such as RCCP and transferring to demand management with my info structure, should I include the standard SOP key figures and is it better to set it as level-by-level rather than consistent?
Dear,
Yes you can do RCCP for self define info structure go to MC35 here you have option to select the self define info structure and then in in MC94 you can use same for capacity planning as per the key figures defined.
Regards,
R.Brahmankar