on 09-11-2008 2:50 PM
Hi sap all,
i configur the purchase req point of *approval limit* changed(means increased) that amount reflect or not how i can i check.i m sd consultant i dont no process in mm so that i want detaieled explenation,that amount reflect or not
how to release the PR & PO.
Thanks and Regards
Raju
Hi,
ME54N - Release PR individually
ME55 - Release PR collectively
ME29N - Release PO individually
ME28 - Release PO collectively