cancel
Showing results for 
Search instead for 
Did you mean: 

How to exclude shutdown period for MRP for a warehouse, or for a specific material group

0 Kudos

Dear All,

We have fairly big operation with several warehouses and plants. During the summer shutdown one of our warehouse shuts down. We would like to run MRP considering this shutdown to generate purchase requisitions, before shutdown period. It's important that some of our warehouses will and should recieve.

Is there a warehouse specific solution for this?

View Entire Topic
DominikTylczyn
Active Contributor

Hello terdyp

MRP is executed on a plant (MRP area) level, not on a warehouse level. You can model a plant shutdown period with the factory calendar by putting the days off there.

Best regards

Dominik Tylczynski