  Dear Experts,

My cost Planning values for WBS same as budgeting.

How can I transfer my plan values from T-code CJ40 to T-code CJ30.

Please suggest,

Thanks,

View Entire Topic
Former Member
0 Kudos

Hi,

CJ30->Open Project->Select the required WBS elements->Menu bar->Edit->Copy View->Select Option 5(Planned Total)->Give 100 if asked for percentage->click on continue icon.

Check if your Planned values will get copied to Original Budget. Then select Budget column->Edit->total up->save.

Also you can use IMCCP3 tranx to copy plan values as suggested above.

Regards

Shishir