How to assign Pm sub assembly in pm main assembly

Former Member
0 Kudos

I was trying to assign pm sub assemby into pm assemby by system giving error message pm assemby not maintained in plant .As pm assemby we are creating with out assingning to any plant.

Advance thanks for solution

REgards

Anand

View Entire Topic
kalyan_chakravarthi6
Active Participant
0 Kudos

Hi Anand,

1.Please create Maintenance Assemblies with the Material Type as IBAU by using the transaction code MM01.

2.Create Equipment BOM by using the transaction code IB01 and give the Item Category as "I" (PM structure element) and enter the Maintenance Assembly number which was created in the earlier step.

As you said in your thread, for IBAU materials there is no plant specific data will be maintained and you can use it for any plant.

Please note that PM assemblies you can not assign in Materail BOM in CS01 transaction code.PM assemblies you can assign only in Equipment BOM (IB01).

Best Regards

Kalyan

Former Member
0 Kudos

Hi Kalyan,

  Tomorrow I will check .Previously i tried to assign in cs01

Wiht best regards

Anandm

Former Member
0 Kudos

Hi Kalyan,

I was able to assign pm assemblt in cs01 as well as ib01 by selecting item category i.

Thanks for your valuble answer.

Regards

Anand