Hi everyone, i allready create my enterprise calendar but i dont know  the process to activate it.

thanks by advance for your answers!

View Entire Topic
kaushalya
Active Participant
0 Kudos

Hi Moise,

If you have created your SAP calendar in DEV server, you have to transport it to Production server.

You can set-up the 2014 calendar by assigning the holidays to your Factory calendar.

Hope this guide >> scn.sap.com/community/erp/blog/2012/12/31/creating-factoryholiday-calendar << will help you!

Former Member
0 Kudos

Hi Kaushalya,

I really appreciate your link,thank you! it is just the answer i was waiting for.

Regards,

kaushalya
Active Participant
0 Kudos

You're welcome! I'm glad it was useful!