on 01-24-2012 5:28 PM
Hi experts,
Does anyone know if there is a function module to release all budget in a project/WBS without having to enter the amount you want release?
I mean, imagine that my WBS has overall budget = 3000 and FY 2011 : 500, FY 2012: 2500, is there any Function to do a release of all buget at the same time without needed to enter the amounts?
Thanks a lot for your help,
Sara
Please check if KWEB_BUDG_ACTION_RELEASE helps.
Regards
Shrikant