on 10-16-2009 9:21 AM
Hi,
I have a 3 systems landscape (DEV, QAS and PRD) and will be upgrading them from 4.7 to ERP6 soon.
I will do a test ERP6 upgrade on my DEV/QAS first and this is expected to take a few months before I upgrade the PRD server.
After upgrading my test servers (DEV and QAS) to ERP6 how can I manage my transport requests between DEV and QAS to PRD since PRD is still on 4.7?
Thanks for any advise.
Hi,
It is not recommended to transport between then systems having different version as object will also have different version.
Thanks
Sunny