Hi,

I have a 3 systems landscape (DEV, QAS and PRD) and will be upgrading them from 4.7 to ERP6 soon.

I will do a test ERP6 upgrade on my DEV/QAS first and this is expected to take a few months before I upgrade the PRD server.

After upgrading my test servers (DEV and QAS) to ERP6 how can I manage my transport requests between DEV and QAS to PRD since PRD is still on 4.7?

Thanks for any advise.

View Entire Topic
sunny_pahuja2
Active Contributor
0 Kudos

Hi,

It is not recommended to transport between then systems having different version as object will also have different version.

Thanks