on 07-10-2014 11:33 AM
Hello experts,
Depending on the material, I have two scenarios:
Sometimes MRP says to reschedule the PO (message 10):
And other times MRP says to cancel a PO and create a new one (message 20):
Why does this happen? According to which data does occur one behavior or another?? Is there any value in the material master??
Thanks in advance.
Laura
Laura,
Exception message 10 generated because requirement on 28/07 but your firmed receipt is on 06/08 which is later than the requirement so as per rescheduling horizon system generates 10 to Reschedule in, if requirement is later than the receipt then system generates 15 to Reschedule out.
Please check SAP note 1745312 which explains about Exception message 20 and Rescheduling horizon functionality.
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.