Difference b/w Planning Strategy 50 nd 52 . and cane u pl give brief explanation of 52 strategy .
Hi Phani
Strategy 50 : The Planned Order/Production Order is Linked with the Sales Order & Once Complete the Production order, Stock will get updated as Special Stock, which is linked/assigned to the Sales Order (Look at the attachment 1)
Strategy 52 : Planned Order/Production Order don't have any Link to the Sales Order & Once complete the Production Order, Stock will get updated into Unrestricted Stock( Not specific to any sales Order) (Look at the attachment 2)
Please find attached screen shots of the same, where you find the sales Order details in the Planned Order ( in case of Strategy 50)
Hope, this is clear to you & kindly let me know, for any other details/assistance required
Many thanks for your quick feedback. Best Regards : Raja Sekhara Reddy B
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.