cancel
Showing results for 
Search instead for 
Did you mean: 

Dependent requirements

Former Member
0 Kudos

Hi Friends,

I have done the Planning run ( Long term planning ) using tcode MS01. it has planned for the finished goods but the dependent requirements are not planned.

What can be the possible reasons???

Naren

View Entire Topic
Former Member
0 Kudos

Dear Narendra

Check u'r long term planning Procedure

1.) Create Planned Independent Requirememts (T.C MD61)

2.) Create Planning Scenario ( T.C MS31)

3.) Create Planning File Entries (T.C MS20)

Then Run Long Term Planning ( T.C MS01).Here Dependent requirements will not be created.Only Simulated requirements (SimReq) will be created.

You can view your stock requirements list through MS04

Reward points if usefull

Regards

Palaniappan

Message was edited by:

Palaniappan Sundaram