on 07-22-2009 8:02 AM
Hi Friends,
I want to check credit for the customer.
We give grace period to customers...
i.e credit check should be done after grace period..
How to map it..
Where to maintain grace period..whether it is payment terms?
with regards
Hi Azeez,
Let us assume that the credit limit period is 30 days and grace period is 15 days .As undersatand your requirement is that the system should block the processing once the period exceeds 45 days.For that to happen goto
ova8
go to the detail screen of your credit control area by double clicking it
against the field oldest open item give 45
this will meet your requirement
The system will pick the date of the sales order if the update group is 000012 which is most widely used.
Regards,
Phani Prasad.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
10 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.