Dear experts
While running the ck11n, system is issuing error like ,No control record for Activity type BP01/A02CA1003/DL2001 in version 000 / 2009 activity planning/qty planning, Please advise how to solve.
Regards
R.Rajakarthik
Dear Raja karthik,
Check whether is the activity rates maintained properly for the activity type and cost center combination
in KP26 for the mentioned period.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Activity types describe the activity produced by a cost center and are measured in units of time or quantity.
In activity type planning, control data determines whether the activity price for evaluation of the activity type is manually set or is derived iteratively through activity price calculation.
You need to define activity type in Workcenter in CR01 / CR02 in Costing Tab.
Hope this clears your doubt.
Regards,
Tejas
User | Count |
---|---|
98 | |
9 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.