i have same group of cost element with mulitpile ptoduct

but diffreent overhead to individual product

how to map the scenarion in cost sheet.

View Entire Topic
Former Member
0 Kudos

Hi,

Looks like you expect to calculate OH based on Material. Well, there is no option to select 'Material' field as a dependency, however, you can include 'Overhead key' as one of the depenency (eg: 'D010') and assign Overhead key to Overhead group. Overhead group in turn can be assigned in Material master Costing view. In other words, you need to maintain as many Overhead keys & Overhead groups as there are number of Materials (one-one relation).