Hello experts
I have done some new configuration in Dev. system and I need to move Quality and Production
Also I came to know some discussions in the form –
Q1: Once we release in Dev. System –how automatically updating the transport request in quality system in STMS.
Q2: After quality Import how automatically updating transport request in production import queue
As we know while releasing we are not giving any target system, still how the target systems are updating with transport request
So can you give some suggestions on these points?
Regards
Ishikesh
hi
it is total depending on basis team,
you question as basis ,
sd consultant configure in development system , and release the transport request to basis team
T code SE01 , you release the request then basis team to move to quality and production .
it totally basis transaction .
like main development system(100) and testing development system(300)
once your configure some thing it comes transport request in 100 client
then test the the configure work or not in test client 400 ,
on that time you use SCC1 t code , when you log in the 400, then give request number , it comes to 100-400 for request , this transfer the data one client to anther client
but basis use T code STMS , in this system transport management system , can trance fer the request development to quality and production.
http://www.freesaptutorial.com/how-to-release-a-transport-request-using-se01/tr/
http://www.freesaptutorial.com/how-to-release-a-transport-request-using-se01/
http://help.sap.com/saphelp_sm40/helpdata/EN/37/791b0026644a6197fe7870361afeff/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.