on 11-30-2023 6:11 AM
Hi experts,
Kindly could someone explain the whole process of settlement of AUC (asset under construction) with the help of WBS element, like creation of WBS element and what is WBS element.
Could some one attach any blog or tag any information that will help in this regard.
Many thanks,
Venkat
Hi,
Kindly follow the test script of scope item 1NT. It has complete details.
It is very simple and explained well in the document.
further help:
Project Profiles | SAP Help Portal (focus on Investment Project)
Regards
Shakeel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can explore scope item 35F : Project control - Capital projects for the same.
regards, Raman Rana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.