on 10-22-2010 3:48 PM
Hi All,
I have searched for related threads for ECC 6.0 but not found, so wrinting this thread.
I am using ECC 6.0 EhP4.
In Budget Report like S_ALR_87013558 and Commitment Report CJI5, system is showing incorrect commitment values against some POs. But for those POs already GRN/IV get posted.
Those POs are for Pre-Upgrade period. Is it related to Upgrade issue?
I have checked some OSS Notes but did not found any Note related to ECC 6.0 EhP4.
If anyone knows regarding this, please let me know. Correction programmes sequence/OSS Notes ?
Also I have tried RKANBU01,CJEN and CJBN in sequence in my Quality system for the same scenario (Copy of Pre-Upgrade). But its not working and some warning Message log is appearing in CJEN - Project Reconstruct Database as " No value category could be determined for commitment item xxx xxx xxxxxx"
Please suggest for the solution as early as possible.
Many Thanks in advance.
Swapnil Kharul
Good Evening Swapnil,
Were you able to resolve this matter? I am currently experiencing similar issue post EHP4 installation in ECC6.
S_ALR_87013558 report shows incorrect commitment values.
Any feedback will be appreciated.
Kind Regards;
Werner
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
The following notes resolves the issue:
1491430 - Incorrect Commitments for Service Items
1492317 - Incorrect commitments after posting service entry sheet
This is a program error for Service PO's created prior to EHP4 upgrade.
PS - Just execute RKANBU01 once notes have been applied. Enter * in Order and Project Fields.
Kind Regards;
Werner