Hello,

I 've got a problem.

I am trying to track every project modification using cn60.

It works for WBS modifications but it doesn't for Project Definition modifications.

I have check the indicator in the project profile and at the data element level.

Any clue about his issue?

Thanks.

Moderation Note - Please do not use capital letters for general text type words. The subject has now been edited

Message was edited by: Virendra Pal

View Entire Topic
Former Member
0 Kudos

Hi,

If you have activated change documents in project profile, please check if the tick is in project profile on the right side. Tik should not be under the status management section

Provided you are having correct tikmark in project profile, then can you go into a project. You can subsequently do changes in master data field. You can then save and then run CN60 to check changes.

Also ensure that Project is released as change documents are not displayed for either created or deleted objects.

Regards

Tushar

0 Kudos

It is released an the tikmark is ok because it works for PRPS table.

I guess i have a problem related only to PROJ table.

former_member203108
Active Contributor
0 Kudos

Change docuemnts will not be recorded for all fields even though you have marked it in project profile. Only those fields whose data elements have change document activated will be recorded.

0 Kudos

Thanks,

that's was checked as well.

It must be something affecting the entire PROJ table.

Former Member
0 Kudos

Hi Jose,

Please confirm if change documents have been activated after creation of project.

Also check if changes in Project definition are carried out in CJ20N...

Additionally, please refer SAP Note 325459 - Change documents in information system

Regards

Tushar