At the time of ck11n cost estimation run. raw material price is not fetching from moving and standard price control... it is considering recent PO material rate.....plz guide me

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi @0025121074 please check your valuation variant & and check the priority of the pricing, probably you have given first priority to take PO (purchasing info records) price.

Neeraj_Jain
Active Contributor
0 Kudos

Hello 0025121074,

Please refer below SAP thread. Hope it's clarifies your query.

https://answers.sap.com/questions/13098314/cost-estimate-run-ck11n.html