CJ8G Results in no data

Former Member
0 Kudos

Hi Gurus

I'm still quite new to SAP PS & cProjects, I'm trying to run a Settlement Process for my Project.

The tasks I have completed so far are:

CAT2 - Time Capture

CATS_APPR_LITE - Time Sheet Approval

CAT7 - CATS Transfer to controlling

SE38 - (DPR_CATS_CPR_TRANSF) - Transfer Time to cProjects

CJI3 - Verify Actual Posted Costs

CJB1 - Generate Settlement Rules

When I then run CJ8G I get no results.

Am I missing config in this area?

Any guidance will be greatly apprecioated.

Regards

Panduranga

View Entire Topic
virendra_pal
Active Contributor
0 Kudos

try running CAT5 (or CATA) to trnafer costs to PS and then run settlement

In your process steps you have transferred costs to c projects but not to R/3 PS