In our present scenario.First we create the PO and if we go for ME9F or For GR without Releaisng of PO it is giving error message PO is not yet release which is OK, but if we release the PO, and after that if we change the PO it is not asking again for PO release my requirement is that after changing in PO system should not allow to ME9F or MIGO it should again ask for PO release, and also how to see the changes made for a particular PO.
regards,
zafar
Hello
In SPRO setting under release Strategy in release indicator you have the standard Options as below.YOu need to select as per requirement.
1 Cannot be changed
2 Changeable, no new determination of strategy
3 Changeable, new release in case of new strategy
4 Changeable, new release in case of new strat. or val. change
5 Changeable, new release if new strategy/outputted
6 Changeable, new rel. if new strat. or value change/outputted
Changeable, new release in case of new strategy
Regarding Change log. You can see in Purchase order from environment go to see Header change.For item level change select the line item which need to be checked.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.