Hi Experts,

Greetings to all...

I wish to ask following question:

I have a material whose profit center is XYZ and I created a PO and after that business asked me to change the profit center for the material so I updated the profit center of the material in "Sale General/Plant Data" and changed the profit center to ABC. During update it shows me warning message "There are atill open purchase order items or schedulling agreements" and I saved the material and profit center got updated.

But during the MIGO of the PO created still shows the profit center as XYZ. So I wanted to ask:

1. Why it is picking old profit center

2. Is there anyway I can change the profit center in MIGO or PO.

Thanking you in advance.

Regards,

UK.

View Entire Topic
tejyadav
Active Contributor
0 Kudos

1. Why it is picking old profit center

Since you changed the profit center after creating the PO that's the reason it is picking old profit center

2. Is there anyway I can change the profit center in MIGO or PO.

No way, you need to delete the PO or the Line item & create new line item in same PO or create New PO.