Change in Valid to date for reources in a recipe

navneet_arora
Explorer
0 Kudos

Hi All,

Need help for below query,

Is it possible to change the valid to date ( it is 31.12.9999 default ) to another date for example 31.12.2016 for the resources in a recipe with or with out change number?

Searched many post but didn't get any answer.

Thanks,

Navneet

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Without change number it is not possible in standard SAP.

Best Regards,

R.Brahmankar

navneet_arora
Explorer
0 Kudos

Hi,

thanks for your reply,

Could you please let me know how to change it with the change number? I have changed the settings to change rule but could not find how to change the valid to date. Checked in  alternative dates in change no. also.

Thanks,

Navneet

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

By using change number you can change valid-from date not Valid to date.

Workaround example Create a change number using CC01 ,having the valid from date as 01.07.2015 and make the changes in recipe

2.Create another separate change number using CC01,having the valid from date as 01.08.2015 and add the phase/operation in recipe

In that case you can view the valid from date as 01.07.2015 to 31.07.2015 .

Please refer,

and KBA 1644885 - Explanation of BOM Validity Date

Best Regards,

R.Brahmanka