Hello,
Without change number it is not possible in standard SAP.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
By using change number you can change valid-from date not Valid to date.
Workaround example Create a change number using CC01 ,having the valid from date as 01.07.2015 and make the changes in recipe
2.Create another separate change number using CC01,having the valid from date as 01.08.2015 and add the phase/operation in recipe
In that case you can view the valid from date as 01.07.2015 to 31.07.2015 .
Please refer,
and KBA 1644885 - Explanation of BOM Validity Date
Best Regards,
R.Brahmanka