change in MRP planning control parameters.

Former Member
0 Kudos

Hi gurus,

i have an issue regarding the control parameters for MRP.

Presently while planning run i am getting some purchase requisitions and some planned orders for externally procured items with create purchase requisition =2( pur req in opening period) with opening period =0.

Hence, we want all the materials( externally procured) to be getting the purchase requisitions without any planned orders at all as the MRP controller can reduce the time converting the planned orders into purcase requisitions.

Can we go for the change in control parameter for create purchase req =1(purchase requisitions).

Please let me know if it has any side effects ????

Thank you in advance.

Naveen.A

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Yes you can do it. You can change the prameter in OPPQ and OPPR also. Same thing you can define in the MD01 or MD02. There is no side effect just you need to run MRP with planing mode -3 deleted and recreated so it will cahnge existing Planned order to PR also.

Regards,

R.Brahmankar