cancel
Showing results for 
Search instead for 
Did you mean: 

Budgeting and Planning

Former Member
0 Kudos

Hello everyone,

can we do the planning and budgeting @ storage location level under a plant?

Can we create a release strategy using a cost centre as a characteristic?

Thanks in advance

Regards

Sachin

View Entire Topic
Former Member
0 Kudos

Cost planning and Budgeting cannot be done at Storage location level.

Budgeting can be done only at WBS level.

regards

Pratap.V