Hi Experts
I have configured budget availability check with Overall+Released.
For the project, i have planned costs using network activities (Commitments are not created yet)
These costs are updated as planned costs and assingned costs in budget overview.
1) I am unable to maintain budget less than 100% (because of assigned costs)
2) I am unable to release for lesser amounts (It is too because of assigned costs)
This way, i am unable to use the functionalties of REVALUATION and PARTIAL RELEASE.
Please suggest possible solution to make use these functions.
warm regards
ramSiva
Goto OPUV, uncheck the assigned value box for order category 20. This will make network planned cost not to be included in assigned value when the system status is CRTD, but once you release the project, the network planned cost will be included in assigned value irrespective of this setting.
Edited by: Ahmed Rifaee on Jan 8, 2010 10:25 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.