on 08-04-2021 11:50 AM
I need to see the report for all components dependent requirements from the mrp run of finished materials. Please provide your knowledge on getting the Header Material from the component in production planning.
Also i need to see the drill down report for list of FG , SFG orders and raw materials which got consumed in those order from bottom to top as we can see in CK11N screen. The report should show like below with order numbers and conumption quantities
MB56 Batch report will be useful if we have batch. Otherwise custom report is best solution
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.