Hello Experts,

how to assign planning calendar to MRP area? Is it possible?

Thank you very much

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can assign a planning calendar for the MRP area at material level. Open your material in MM02, select your MRP area and you will find the field "planning calendar" under tab MRP2. You can also use the report RMMDDIBE to set the planning calendar for MRP areas of multiple materials.