01-21-2009 10:11 AM
Hi buddies,
I have moved certain TRs from development to the quality server. I need to move these TRs from the quality to the production server. But before that I need to merge these TRs in Quality. Could someone help me out on how to go about this.
Thanks in advance,
Dikshitha
01-21-2009 10:21 AM
Thanks a lot friends for your quick response :).
I just want to confirm about the order of the TRs. Wont that be a problem in production if I merge ? I have around 15 to 20 TRs.
Please help.
01-21-2009 10:12 AM
01-21-2009 10:13 AM
01-21-2009 10:17 AM
Hi
I dont think we can merge the requests in Quality Server.
We can do the same in DEV.
Regards
Shiva
01-21-2009 10:17 AM
Normally you cannot merge on QA system. Merge on DEV system with SE03 as described and transport to both QA and PRD.
Make sure that none of the included objects has subsequently been changed in DEV.
Afterwards the now obsolete single transports should be deleted from the PRD import queue.
Thomas
01-21-2009 10:21 AM
Thanks a lot friends for your quick response :).
I just want to confirm about the order of the TRs. Wont that be a problem in production if I merge ? I have around 15 to 20 TRs.
Please help.
01-21-2009 10:26 AM
Hi
You need to maintain the sequence of TR release. The dependent must be released first.
We need to be very careful before merging the TRs.
Try to merge the related objects.
Regards
Shiva