04-21-2013 7:53 PM
Hello All,
I am allocating an resource to an activity of a project through transaction CM27. Now based on the value of the Activity I need to to allocate the same resource to some other activity of the same project. I am trying that with FM 'CY_BT_KBED_OPR_UPDATE'. but I am not able to update 2nd actvity. Can some one help me on doing this with this function module or some other?
04-22-2013 6:56 AM
Hi,
Try the BAPI BAPI_PROJECT_MAINTAIN and BAPI_NETWORK_MAINTAIN. Check the function groups 2001, 2002 and 2054.
Cheers
~Niranjan
04-22-2013 5:53 PM
I think these 2 bapis does not have fields for resource allocation(updation of KBED table).